Boiler Upgrade Scheme: November 2026 installer update
16 November 2026
What November's £520m BUS voucher allocation approval means for installers in England and Wales, with guidance dates and practical application-file checks.

The Boiler Upgrade Scheme November 2026 update allows Ofgem to allocate vouchers up to £520 million in the current financial year. DESNZ published the approval on 5 November 2026. For installers in England and Wales, this changes the scheme-level allocation limit; it does not itself approve a customer's application or guarantee payment for an installation.
Published: 16 November 2026. Last reviewed: 16 November 2026.
What changed in the Boiler Upgrade Scheme in November 2026?
DESNZ's approval to over-allocate BUS vouchers is a confirmed permission, not a consultation. It allows vouchers with a total value up to £520 million to be issued in this financial year. DESNZ says that, based on expected redemption rates, spending should remain within the £400 million scheme budget.
Those figures describe two different controls: the value of vouchers allocated and the budget available for spending. An installer should not interpret £520 million as a new grant pot that has already been paid out. The practical consequence is to keep allocation, application approval and redemption as separate stages in the sales and delivery pipeline.
The notice applies to BUS, which operates in England and Wales. Do not use this announcement to advertise the same offer to projects in Scotland or Northern Ireland. It is relevant to heating installation businesses handling BUS applications, and to their sales, administration and finance teams.
Use the application date to select the guidance
Ofgem's installer guidance page, first published 9 April 2025 and updated 3 November 2026, identifies version 5.2 as current. It applies to applications properly made on or after 28 April 2026, when regulation changes took effect. The page retains version 4.2 for applications properly made before that date.
Ofgem also identifies 21 July 2026 as the start date for uplifted grant values for eligible off-gas-grid properties. That is a separate earlier change, not a benefit introduced by the November allocation notice. Before putting a grant figure into a quote, check the property's eligibility and the guidance that applies to the application.
A voucher application is only “properly made” when Ofgem has the necessary information to assess eligibility, along with consent and identity verification. Redemption also needs all required information. An initial submission date is therefore not a safe substitute for the properly-made date when information remains outstanding.
Put five checks in every BUS project file
| Check | What the business should record | Why it matters |
|---|---|---|
| Property and scope | Nation, proposed technology and eligibility evidence | A national budget notice does not establish project eligibility |
| Applicable guidance | Version used and the properly-made application date | Old and new applications can follow different guidance |
| Customer quotation | Grant assumption, customer contribution and the conditions used | Stops sales copy becoming an unconditional funding promise |
| Voucher administration | Status, outstanding information, deadlines and responsible person | An incomplete file can hold up assessment |
| Redemption and payment | Required installation evidence, submission status and payment reconciliation | An allocated voucher is not cash received |
Use the detailed current guidance for technology eligibility, grant values, voucher conditions, account administration and audit requirements. Copy the conditions that apply to the actual project into its file rather than using a general marketing summary as the operating instruction.
Worked example: a quote crossing a guidance boundary
Suppose an installer submitted an application on 24 April 2026, but missing information was supplied later. The administrator should establish when the application became properly made before choosing a guidance version. Selecting version 4.2 solely because the first form was sent before 28 April could be wrong.
For a separate November enquiry, the estimator can acknowledge the new allocation permission while still making the quote's grant assumption conditional on eligibility and the application outcome. The finance team should track redemption and payment separately from the sales team's list of expected vouchers. This avoids counting a scheme announcement as committed revenue.
What to recheck before your next quote
Recheck Ofgem's current guidance and any new DESNZ allocation notice before quoting, applying or redeeming. In particular, recheck when an application crosses a rule-change date, the property may qualify for an uplift, or the financial year changes. This article does not replace the project's applicable guidance; ask Ofgem about an application-specific eligibility or processing question.
For a related operational task, read our MCS installer transition checklist once your business is planning its certification transition.
Primary sources
- DESNZ: BUS over-allocation approval, published 5 November 2026; England and Wales.
- Ofgem: BUS guidance for installers, published 9 April 2025; last updated 3 November 2026. The page links the current version 5.2 and earlier version 4.2.